|
ABSTRACT
Farmer motivation for building and operating anaerobic
digesters has expanded from solely energy benefits to include manure treatment
cost savings, nutrient conversion, odor and pathogen control, and byproduct
recovery. The AgSTAR Program is
sponsored by the USEPA, USDA and USDOE to encourage farm methane recovery from
anaerobic digestion. AgSTAR has
provided technical assistance to over 14 farms to assist them through the
development, installation, start-up and operating phases of their anaerobic
digestion projects. Three
dairy plug flow digesters (NY, CT, OR), four covered pig manure lagoons (NC,
VA, IA, MS) and three heated mixed pig manure digester (CO, IO,IL) have been
placed in operation since January 1997 with AgSTAR technical assistance.
The farms and their digester systems are described.
The cost of the digester systems are summarized.
Biogas recovery and use in boilers or engine-generators is discussed
for each farm. Start up and
operational lessons learned are presented.
Keywords:
Biogas, methane, odor, anaerobic digestion, digester, covered lagoon,
nutrient management, pathogens
Introduction
Anaerobic digestion is more extensively used outside of
the US where treatment of animal waste has been
a concern for a longer time. An
anaerobic digester is a vessel designed to retain decomposing manure for
sufficient time at the designed operating temperature to allow the growth of
methanogenic bacteria in a “steady-state”.
Electricity and heat production are direct benefits of anaerobic
digestion. The effluent of a digester has an earthy smell with some ammonia
present. The first dairy digester systems in the US were installed principally
to produce energy during the energy crisis.
The first pig manure digester systems in the US were installed
principally to control manure odors. Today, farmer motivation for building and
operating anaerobic digesters has expanded from direct energy benefits to
include key non-energy benefits such as: odor control, improved manure
handling, mineralization of
organic nitrogen, weed seed destruction, pathogen reduction and byproduct
production such as digested dairy solids.
AgSTAR is a voluntary program sponsored by the US
Environmental Protection Agency (EPA), the US Department of Agriculture -
Natural Resources Conservation Service (NRCS) and the US Department of Energy
(DOE), to encourage methane capture as a part of manure management.
Since 1996, AgSTAR provided technical support to 14 AgSTAR Partner
farms who were developing anaerobic digester systems.
The system installation, operation and benefits are described.
A summary table by type of digester is presented to allow comparisons
of costs.
COMPLETE MIX DIGESTERS
Complete mix digesters are used to treat waste with 3 to
10% total solids and adequate volatile solids to produce enough biogas methane
to maintain digester temperature. Three
complete mix digesters were built on farms with pull plug manure collection.
The digesters are described, benefits enumerated and a summary table allows
comparison of costs and benefits. All are heated with biogas heated water and
mixed to maintain a high level of bacterial activity. All of the units are
built in cold climates. All units
represent a cost savings over using an ambient temperature lagoon designed to
Natural Resources Conservation Service (NRCS) or American Society of
Agricultural Engineers (ASAE) standards to perform the same level of treatment
for odor control. Ambient
temperature lagoons would be 10-20 times larger than these digesters to
perform the same function. The
design and operation goal of the Apex Digester is consistent biological
stabilization of waste and odor control, while the goal of Colorado Pork and
Swine USA is optimization of biogas production and use while stabilizing the
waste.
Apex Pork - 8,600 Head Pig Finishing Facility,
Rio, IL
Apex Pork has 8,600 hogs in 9 buildings with pull plug
manure collection. Three years of
seasonal odor episodes from the manure storage pond were not acceptable to
downwind neighbors. The farm chose Resource Conservation Management, Inc. to
design an innovative, low cost, heated, mixed covered earthen lagoon digester.
A bank-buried insulated floating cover is installed on the 36.3 x 48.5
x 5 meter lagoon which can hold roughly 20 days worth of manure. The digester
produces enough methane to fuel a boiler to heat the digester and flares
unused methane. Stabilized
digester effluent flows to the storage pond.
The pond no longer emits odorous gases. The primary benefits to the
owners are odor reduction of stored and field applied manure. There have been
no odor complaints since the digester was installed. Compliance investigations
by state regulators stopped. The digester is able to accomodate the variation
in manure loading rate that results from all-in-all-out operation.
The digester started up in about 30 days switching to
biogas from propane in June 1998. By mid summer, 1998 the system was producing
36,000 ft3 of biogas per day. The unit was running well when a microburst
damaged the gas collection cover and nearby buildings in August 1998.
The partial cover was replaced with a bank attached floating cover over
the whole lagoon in October 1998. Concurrently
the farm was emptied of pigs to allow building renovations and a change of pig
flow. The farm, originally a continuous flow facility, converted to
all-in-all-out operations. Digester heating began in December 28, 1998.
January 24, 1999 in midwinter temperatures the boiler system was
switched to biogas and has run full time with little or no maintenance since.
The digester was gained temperature during the coldest times of the year. The
digester has been through 3 grow-out cycles without problems.
The system is simple to operate and the owner only spends about 10
minutes daily to check the system.
Several lessons of this project were: 1. A bank-buried complete lagoon
cover, though a more expensive first cost, is less expensive to maintain than
a floating edge partial cover. 2. Inexpensive cover materials such as 20 mill HDPE coated
fabric are can present problems in extreme weather.
3. Pig operations can
change rapidly and radically and present a completely different waste stream.
The farms are very similar in size and operation.
Colorado Pork has about 600 more pigs growing as replacement gilts.
However, the farm buildings and equipment are different.
Both facilities were built from 1997-8 on sites that had been range or
pasture. Environmental concerns of neighbors and state authorities
prompted both owners to weigh waste management alternatives. Both chose complete mix digesters with separate storage to:
1. biologically stabilize manure,
eliminate odor and optimize methane recovery for electricity production. 2.
reduce their investment in waste management and 3. avoid problems with
regulators by installing an environmentally beneficial system.
Periodically,
plugs are drained to a concrete collection tank and then pumped to the
2,100-2,200 m3 concrete tank digesters. The digesters are heated, mixed and
covered by two biogas inflated plastic gas collection domes. Effluent at
Colorado Pork flows into a nearly basin to be evaporated, while SWUSA effluent
is stored in 2 concrete tanks for annual application to cropland.
Biogas fuels Caterpillar 3306 engines attached to 80 kW generators.
All electricity produced is used on the farms. Heat, recovered as hot
water from the engine and exhaust, is used to maintain the appropriate
temperature in the digester. Biogas is automatically flared when not being
used by the engine (for example during maintenance).
The farms produce up to 60% of their own electricity needs. The farms are not expected to have surplus electricity to
sell to the utility and do not have sale metering.
The farms chose not to sell electricity rather than submit to
uneconomical requirements and controls of the utility company. Future plans
include using excess heat in the farrowing barns.
The Colorado Pork digester heating began using natural
gas to fuel the generator in August 6, 1999. System operations on biogas began
late September 1999. The digester has been problem-free. The engine has had
typical startup mechanical problems, however, the unit has been operating
continuously. In the first 5 months, the generator operated over 90% of the
time, burning 1.7 million cubic feet of biogas and producing 140,000 kWh of
power 50 kW avg. The system
output increased to 67 kW after 2
bad sensors were found and fixed.
The SWUSA digester was filled and heated over a 90-day
period and started biogas production in August 1999, after delays due to
additional construction on the digester tank.
Full biogas yield was reached in September 1999.
The digester has been virtually trouble free.
The generator has operated 77% of the time during the first 6 months
yielding 2,268,000 ft3 biogas with an electricity output average of 67 kW.
Typical startup issues of bad sensors cropped up.
The engine was rebuilt under warranty after a breakdown due to loss of
coolant. The system had a manure
spill reach a ditch through a drain added by contractors. The local utility
and the larger transmission and distribution utility were inconsistent on
intertie requirements. All
generator equipment should be tested prior to being shipped to the site.
The methane recovery system at both Colorado Pork and
SWUSA has diminished farm costs of production by reducing the quantity of
electricity purchased, while greatly improving site odors and contributing to
the farm’s environmentally sound manure management strategy. At SWUSA, the digester is producing about $46,600 worth of
electricity at $0.09/kWh. The
annual value of electricity produced at Colorado Pork is estimated to be
$34,800 based on $0.07/kWh.
Apex paid for all labor and material except AgSTAR
assistance during cover installation, start-up and minor troubleshooting.
Total cost off all work and changes was $152,300 or $17.75 per finisher space.
Operation and maintenance costs have been less than $1000 per year for
electricity and boiler servicing. Colorado Pork paid all project costs except
AgSTAR technical assistance. The
installed cost was $368,000 or $73.60 per sow.
SWUSA received a 100% grant for the project plus AgSTAR technical
assistance. The undifferentiated installed cost was $576,000 or $115.20 per
sow. Given the similarities of the systems, the author has
no explanation for the reported $208,000 difference in system costs.
Maintenance for either systems is estimated at $8,000 per year ($0.015/kWh).
Table 1 summarizes the costs and benefits of these systems.
|
|
Table 1. Complete Mix Digester Costs And Benefits
|
|
|
|
|
|
Apex
|
Colorado
Pork
|
|
|
|
|
|
$
29,000
|
$
13,900
|
b
|
|
|
|
|
$
0
|
$
0a
|
b
|
|
|
Digester and equipment
|
|
|
$
66,700
|
$
191,200
|
b
|
|
|
Engine-generator
|
$
0
|
$
67,000c
|
b
|
|
|
Boiler
|
|
|
$ 10,900
|
$
0
|
b
|
|
|
Electrical/
|
intertie
|
|
$
2,200
|
$
17,600
|
b
|
|
|
Energy building, plumbing, elec.
|
$
11,500
|
$
35,400
|
b
|
|
|
|
Subtotal
|
$ 117,300
|
$ 325,100
|
b
|
|
|
Private Engineers
|
|
$
10,000
|
$
8,900
|
b
|
|
|
Engineer (AgSTAR)
|
|
$
15,000
|
$
30,000
|
$30,000
|
|
|
Startup
|
|
|
$
7,000
|
$
4,000
|
b
|
|
|
|
Total Cost
|
$
152,300
|
$
368,000
|
$576,000
|
|
|
BENEFITS
|
|
|
|
|
|
|
Electricity
|
|
0
|
34800
|
46600
|
|
|
Heat Energy
|
|
0
|
|
|
|
|
|
Total
|
0
|
34800
|
46600
|
|
|
|
|
|
|
|
|
|
a.
Included in digester
b.
Breakdown not available
c.
Reconditioned equipment
PLUG FLOW DIGESTERS
Plug flow digesters are used to treat scraped manure from
dairies. Over the past 4 years,
three 1,000 cow digesters have been built. The digesters are described,
benefits enumerated and a summary table allows comparison of costs and
benefits.
Craven Dairy Farm, Cloverdale, Oregon – 1,000 cow
digester
Craven Farms completed a heated, unmixed, plug flow
digester sized for the daily manure production of 1000 cows in December 1996.
The winter startup was not a difficult problem.
The digester performed without incident. The used engine generators presented many challenges and
required a lot of small repairs. However,
the used generators were $50,000 cost saving over new units.
The digester peaked when treating manure from 750 cows on site and 250
cows worth of manure from neighboring dairies.
In November 1999 the farm was sold.
The owner is expected to move in and begin operations in summer of
2000.
The digester produced about $ 24,000 of electricity and $
30,000 of digester fiber yearly. The
value of digested solids is twice the original estimates.
The digester eased manure handling and reduced the cost of application.
It appears that the digested liquids produced a higher quality hay than
previous manure nutrient management.
Pathogen concentrations were reduced.
Odors were reduced substantially as reported by the neighbors.
AA Dairy, Candor,
New York - 1000 cow digester
AA Dairy Farm of built and started up a at their 550 cow
facility, completing a boiler fired system in October 1997.
The digester is sized for planned expansion.
AgSTAR provided technical assistance in all phases of the project.
Issues with New York State Electric and Gas Co. over a used intertie
panel previously approved in Pennsylvania delayed engine-generator startup
until June 1998. Modifying the
previously approved panel to conform to NYSEG wishes cost the owner $21,000.
Additional issues have arisen over NYSEG punitive insurance
requirements that are being resolved.
The digester has operated without problems.
The engine has had occasional outages for repair.
In total the generator is operating over 90% of the time. The system is
currently producing 70 kWh, hot water and about $60/day of digested fiber.
Odor has been controlled. The
cost of manure application is substantially reduced.
Haubenschild Dairy,
Princeton, Minnesota - 1000 cow digester
Haubenschild Dairy Farm started up a at their 480 cow
facility while currently completing their expansion to 1,000 cows completing a
boiler fired system in October 1999. The
major challenge was from the generator company who delayed equipment delivery,
hence system startup for months. The utility, Steele-Waseca Cooperative has
been a promoter of and asset to the project. The project has been well received and promoted within the
state. The dairy has chosen to
wait to install a separator to recover solids for resale.
The digester has operated without problems.
The engine has had occasional outages for adjustment.
The generator is operating over 95% of the time. The system is
currently producing 70 kWh and hot water to keep the milking parlor warm. Odor
has been controlled. Manure
handling is much easier for the owner.
Table 2shows their costs and benefits.
The cost variation between the systems depends mostly on equipment that
the farms already owned and the engine-generator.
The benefits depend on the value of electricity and the value of
byproduct fiber and heat. AA Dairy funding included a $90,000 grant from the
local Soil Conservation District to improve manure management and the balance
of the cost from the owner.
|
|
Table 2. 1,000 Cow Digester Costs and Benefits
|
|
|
|
|
|
Craven
|
AA Dairy
|
|
|
|
|
|
$
9,500a
|
$
12,500a
|
$
29,505
|
|
|
Digester
|
|
|
$
128,000
|
$
121,000
|
$
111,313
|
|
|
Engine-generator
|
$
50,000b
|
$
32,000b
|
$
119,788
|
|
|
Electrical/
|
intertie
|
|
$
12,200
|
$
33,200
|
Incl w
engine
|
|
|
Energy building, plumbing, elec.
|
$
24,100
|
$
30,500
|
$
35,245
|
|
|
|
Subtotal
|
$ 223,800
|
$ 229,200
|
$ 295,851
|
|
|
Solids Separation
|
|
$
34,000
|
$
38,000
|
0
|
|
|
Engineering (AgSTAR)
|
|
$
24,000
|
$
24,000
|
$
30,000
|
|
|
Startup
|
|
|
$
5,500
|
$
4,500
|
$
4,000
|
|
|
|
|
|
$
287,300
|
$ 295,700
|
$
329,851
|
|
|
BENEFITS
|
|
|
|
|
|
|
Electricity
|
|
$
24,000
|
$
30,000
|
$38,400
|
|
|
Digested fiber
|
|
$
30,000
|
$
21,900
|
0
|
|
|
Heat energy
|
|
$
0
|
$
3,500
|
$5,000
|
|
|
|
Total
|
$
54,000
|
$
55,400
|
$43,400
|
|
|
|
|
|
|
|
|
a.
Pump and wiring, no concrete
b.
Reconditioned, used equipment
|